FIELD NOTES / TIME & MATERIALS
Labor and material cost estimation
Internal labor cost = hours × internal hourly cost; labor charge = hours × the agreed customer rate. For 3.5 hours at $32 cost and $85 billable rate, labor costs $112.00 and the customer charge is $297.50. The difference is not net profit. A T&M bill totals agreed charges; an internal estimate starts with your costs.
Open the free time and materials calculator to total agreed customer charges.
Hypothetical examples in USD; not customer records or recommended rates. Amounts are rounded to cents per line. Read the calculation conventions and check job scope and applicable tax independently.
Start with two distinct rates
Suppose a technician costs you $32 per hour and the agreed customer rate is $85 per hour. For 3.5 hours, your direct labor cost is $112.00 and the labor charge is $297.50. The $185.50 difference is not automatically net profit: overhead, non-billable time and other expenses still matter.
Extend each material line
Multiply quantity by unit amount, then round the line to cents. Six fittings at a $7.25 internal cost are $43.50 of materials cost. At an agreed $9.50 billable unit price, the customer charge is $57.00. Waste or spare stock belongs in your cost assumptions; only charge quantities consistent with your agreement.
| Charge | Basis | Amount |
|---|---|---|
| Labor | 3.5 × $85.00 | $297.50 |
| Fittings | 6 × $9.50 | $57.00 |
| Travel fee | 1 × $25.00 | $25.00 |
| Subtotal | $379.50 | |
| Discount | 5% | −$18.98 |
| After discount | $360.52 | |
| Illustrative tax | 8% of all discounted charges | $28.84 |
| Total charge | $389.36 |
Use the right calculator for the question
The T&M calculator accepts billable prices and produces a customer charge. It cannot infer your profit because it does not collect your internal costs. The job pricing calculator begins with costs and compares the result with a profit target.
Before you share an itemized summary
- Confirm the dates, work description and approval for additional work.
- Separate hours from material quantities; use consistent units.
- Make sure fees were agreed and not already included in rates.
- Check tax treatment independently. The example taxes all charges for illustration.
- Keep supporting records; a calculated total is not evidence of work performed or payment received.